NDT Jiangsu Rudong 800MW Offshore Wind Power Project (H4#, H7#) Put into Operation at Full Capacity
Date:2022-02-26 | Hits:1968
At 15:18 on December 9, 2021, with the successful grid connection of 88# wind turbines of H7# project, all 200 wind turbines of NIT's Jiangsu Rudong 800MW offshore wind power project (H4# and H7#) were connected to the grid for power generation, which marked that the offshore wind power project cluster with the largest single capacity, the largest number of turbines, the farthest offshore distance and the longest 220KV sea cable route among the domestic offshore wind power projects under construction had achieved full capacity and put into operation, and fully completed the set target of "electricity price protection" within the year.
Jiangsu Rudong 800MW offshore wind power project (H4#, H7#) is invested and built by NIT Rudong He Feng Offshore Wind Power Co. Rudong H4# and H7# projects are both 400MW in installed capacity, with 100 wind turbines of 4MW individual capacity respectively. After the completion of the project, 200 wind turbines will be competing for the wind in the Yellow Sea, the "Gemini" offshore booster stations will echo each other, and the "twin" onshore centralized control center will reflect each other. The project is expected to generate about 2.5 billion kWh of electricity annually, which can save nearly 800,000 tons of standard coal and reduce more than 1.9 million tons of pollutant emissions compared with the same level of coal power, which is of great significance to the implementation of the national "3060" target, promoting the green development of the Group and accelerating the construction of a world class clean energy enterprise with global competitiveness.
During the construction period, the project was affected by "bad weather", "offshore wind power rush" and repeated epidemics. In the face of the severe situation, the main leaders of Jiangsu Company went to the site every month to hold high-level coordination meetings, the leaders in charge of the team stationed at the site in Rudong, to establish a rapid communication response mechanism to efficiently solve the project construction problems; the main leaders of the company united to lead all staff, resolutely implement the Group's "annual target can not change, the tasks can not be reduced" work Requirements, night and day, work together, with firm political belief and strong mission to bear, focus on practicing the "six common" target requirements, vigorously implement the "party building + project full capacity into production" special activities, grasp the difficult points, focus on key points, management points, one by one to crack the construction We have coordinated 8 piling vessels, 12 wind turbine hoisting vessels and 13 35kv submarine cable laying vessels to enter the construction site, which played a decisive role in ensuring that the project will be put into operation at full capacity within the year; Huakan Institute, Shanghai Electric, Zhongtian Technology and Jiangsu Haili and other participating construction units and main supply units have pooled their resources and collaborated with each other to concentrate on piling construction, wind turbine hoisting, electrical installation and commissioning. During the construction process, the project has completed the installation of the single module 3,900-ton offshore booster station "twin blocks" within 48 hours, the installation of steel pipe piles "five in one day", the installation of steel pipe piles, and the installation of the main unit. "Five piles in one day", 29 piles sunk in a single month, wind turbines "six cranes in one day", 49 cranes in a single month, 85 35KV submarine cable laying in a single month and many other new domestic offshore wind power construction records, for the project's full capacity to put into operation, completely win The project has provided a strong guarantee for the full capacity of the project to be put into operation and win the battle of "electricity price protection".
The full-capacity commissioning of Rudong 800MW offshore wind power project (H4# and H7#) marks the full-capacity commissioning of the three tariff-protecting projects approved by the company at the end of 2018 (a total of 1100MW), following the full-capacity commissioning of the NIDEC Binhai South H3# project (300MW) at the end of 2020, within the established time frame, completing the "tariff-protecting "The company's "Thirteenth Five-Year Plan" offshore wind power construction is a perfect conclusion! By now, the installed capacity of all offshore wind power projects has reached 1600MW, which is another step towards the goal of "2030". Among them, Binhai South H3# project has been included in the national renewable energy generation subsidy project list at the end of November this year, and exceeded the annual profit.
All along, the company has always strengthened the responsibility of the central enterprises, bearing in mind the "leader of the offshore wind power" and "elite troops" of the ardent mandate, and strive to implement the "red sea wind people, green energy dream" of the corporate vision to "open up the road in every mountain, set up a bridge in case of water" persistent tenacity and "open up the territory and start again" strong mission, fully implement the Jiangsu company "124" work ideas, with practical action to help the Group's "2035 first-class strategy" to make a new and greater contribution to the early realization.
(Source: Xiang Ying, Rudong He Feng Company)